Notice is hereby given that due to roadworks taking place on the R43 between Botriver and Hermanus, publics within the route may subsequently be affected by road closures and delays as detailed in the below schedule provided by the contractor and project specification directed by the Provincial Government:
Saturday, 13 February 2016: A ‘Stop/Go’ system will operate between 09h00 – 16h00.
Thursday, 18 February to Thursday, 31 March 2016 (INCLUDING SATURDAYS WITHIN THE PERIOD): A ‘Stop/Go’ system will operate between 09h00 – 16h00.
The contractor has advised that the road in the vicinity of the Vermont intersection and Sandbaai Intersection in Hermanus will be mostly affected during this time.
Further notification will be issued as, and when, any amendments to the above are brought to our attention.
Media enquiries: Charmaine Resandt
PRO to the Executive Mayor Nicolette Botha-Guthrie
Tel: 028 313 8023
Email: This email address is being protected from spambots. You need JavaScript enabled to view it.